zhushui sludge treatment enter the countdown
发布于2017-06-20 09:13
点击:次
guangzhou zhujiang cement co., ltd. disposal of dry sludge project progressing smoothly. our company undertakes the project to accept, store and transport the sludge into the kiln for the installation of the equipment and the construction and equipment related to the transformation, electrical, piping and non-standard production and installation. the project plans to start 6.25 test, 6.28 linkage test material. since 6.16, the company conducted a total mobilization, the input of more than 100 people to ensure that the target on schedule to achieve.
by li xiaoxin