argentina technical services project begins
发布于2018-12-27 11:26
点击:次
argentina lamali line 2 5800 tpd cement production line project is located in argentina, buenos aires, olavarria, camino real a 16 de julio s/n, paraje la pampita. b7463 cga. we dispatch qualified technical teams to provide professional technical guidance services to assist party a in the installation, construction, commissioning and performance evaluation of the argentina l'amali line 25800tpd project production line contracted by party a.
no. 3 kiln pier (top support)
clinker warehouse (sliding form construction)
tower, kiln pier foundation (with acceptance)
connection point with old line
preheater tower concrete structure (top concrete completed pouring)
55t crawler crane assembly completed